| Extended
Stay America
Huntington Beach, CA
Serving
as a new prototype for the owner, this three-story 150,000 square
foot hotel, including wood frame and site preparation, was Day Construction’s
fourth project for Extended Stay America.
Prior
to starting construction, the City Building Department required
extensive changes to the architectural drawings. Day Construction
expedited the production of the documents for the City Building
Department by initiating meetings with the architect and coordinating
delivery of the documents to the City. The result was a much quicker
approval process and plan check delays were minimized.
Once
construction commenced, Day Construction had to minimize disruption
to the adjacent Boeing facility and their employees. By holding
on-site meetings with Boeing representatives, Day Construction kept
them abreast of upcoming activities and conditions related to the
hotel’s construction. This communication ensured there were
no surprises and potential disruptions could be effectively managed.
Construction was completed, including extensive landscaping next
to the Boeing parking lot, without disruption to Boeing’s
operations or employees.
Owner:
Extended Stay America
Architect:
MCG Architects
|