Theatre, Simi Valley, CA
Day
Construction’s third project for Regal Cinema Group, construction
of this 60,000 square foot theatre with 16 movie screens was completed
within 180 days.
To
remain on schedule and complete this project in the tight timeline,
Day Construction leveraged its expertise and creativity. In an effort
to make the most of the available work time, an innovative plan
was devised to construct the building from each end, meeting at
the center. This plan allowed the masonry walls to be constructed
at the perimeter while the time-consuming work at the center core
underground was being roughed in. Work was performed during the
night shift to minimize disturbing the residential development and
critical design issues were resolved onsite to keep the project
on schedule.
Owner:
Regal Cinema
Architect:
Casco |
>>