Verizon,
Woodland Hills, CA
This
remodel of an existing competitor’s store into
a Verizon facility was Day Construction’s fifth
project for Verizon Wireless. The project schedule was
eight weeks while the store was to remain open and fully
operational during construction.
To
accommodate Verizon’s schedule and minimize disruption
to the retail operation, Day Construction devised a
plan to barricade 1/2 the store, completing the remodel
in that section and opening it for business, then barricading
and completing the last half. The work was performed
on night shifts, starting at 10:00pm and completing
construction and clean up by the store’s opening
at 10:00am. The project was completed on schedule and
the retail operation was not impacted during construction.
Owner:
Verizon Wireless
Architect:
H. Hendy & Associates
|
>>
Project Photos
|

Click
to enlarge photo
|
|